Loaf Leeds Ventilation System Installation

Redbrick Mill, 218 Bradford Road, Batley WF17 6JF

This project involved the installation of a new ventilation system within a converted mill, now a retail shop. The design incorporated exposed ductwork to align with the industrial aesthetic of the space. While the project presented challenges, our experienced engineers successfully completed the installation to the highest standards. We are pleased to report a satisfied customer. We plan to revisit the site to capture photographs of the completed shop once the interior fit-out is finalized.

Service:

Installation of a new exposed ductwork ventilation system.

Start Date:

June 1, 2023

Completion Date:

July 28, 2023